Debates and Issues raised in Rajya-Sabha

MINISTRY OF RAILWAYS
10/August/2018
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
RAJYA SABHA
UNSTARRED QUESTION NO: 2850
ANSWERED ON:  10.08.2018
Development of high density corridors under PPP mode
Dr. Vikas Mahatme
Will the Minister of RAILWAYS be pleased to state
Will the Minister of RAILWAYS be pleased to state :-

(a) the number of projects, if any, undertaken under the PPP mode for development of high density corridors along with the details thereof;

(b) whether the number of goods trains between major commercial and industrial centres and between collieries and power stations had increased; and

(c) if so, the details thereof?


ANSWER

MINISTER OF STATE IN THE MINISTRY OF RAILWAYS 
(SHRI RAJEN GOHAIN)

(a): Part of the East Coast high-density corridor Bhadrak-Nergundi (67 km) third-line project, has been identified for execution in Public Private Partnership (PPP) mode. Further, 17 Rail Connectivity Projects (including 3 Non Government Railway) have also been taken up with private and public-sector partners under participative policy of Ministry of Railways connecting Ports, Mines and Industrial Clusters under first mile and last mile connectivity.

(b) and (c): Yes, Sir. Average number of rakes loaded per day on Indian Railways has increased from 937 in 2016-17 to 977 in 2017-18. Average number of Coal rakes loaded per day for power houses has increased from 253 in 2016-17 to 258 in 2017-18.  
• State Government to release the entire undisbursed payment of compensation, quantified as Rs 5 Lakhs each, to all affected persons, within three months.

?



Source: